DMC/SandT/13/03
'''England'''
'''Wuhan Ocean Economic & Technical Cooperation Co Ltd v Schiffahrts-Gesellschaft “Hansa Murcia” MBH & Co KG
English Queen’s Bench (Commercial Court): Cooke J: [2012] EWHC 3104 (Comm): 6 November 2012:[[http://www.onlinedmc.co.uk/index.php/Wuhan_Ocean_v_Hansa Murcia]]'''
'''ARBITRATION: CONTRACT FOR CONSTRUCTION OF VESSEL: ADDENDUM FOR SELLERS TO OBTAIN EXTENSION OF REFUND GUARANTEE: IMPLIED TERM TO OBTAIN EXTENSION WITHIN REASONABLE TIME BEFORE EXPIRY OF ORIGINAL GUARANTEE: INNOMINATE TERM: BUT BREACH OF IMPLIED TERM NOT A REPUDIATORY BREACH AS, UNDER THE TERMS OF THE GUARANTEE, BUYERS COULD MAINTAIN THE SECURITY BY COMMENCING ARBITRATION'''