SLB & Ors v PAK & Ors

From DMC
Jump to navigationJump to search

DMC/SandT/26/18

England

SLB & Ors v PAK & Ors

English Commercial Court: Calver J: [2026] EWHC 449 (Comm): 2 March 2026

Judgment Available on BAILII @ https://www.bailii.org/ew/cases/EWHC/Comm/2026/449.html

Michael Ashcroft KC and Socrates Papadopoulos (instructed by Norton Rose Fulbright LLP) and Richard Southern KC and Marcus Mander (instructed by Reed Smith LLP) for SLB and others (Buyers)

Sean O’Sullivan KC, Alexander Wright KC and Henry Ellis (instructed by Stephenson Harwood LLP) for PAK and others (Yards/Sellers)

SHIPBUILDING CONTRACTS: YARDS/SELLERS OBLIGED TO PROVIDE REFUND GUARANTEES WITHIN 120 DAYS, OR SUCH LATER DATE AS BUYERS DESIGNATE, OF NOVATION OF CONTRACTS: YARDS/SELLERS DID NOT PROVIDE GUARANTEES IN TIME: BUYERS CANCELLED CONTRACTS AND CLAIMED LOSS OF BARGAIN DAMAGES: WHETHER PROVIDING GUARANTEES A CONDITION OR INNOMINATE TERM OF CONTRACTS: ARBITRATION ACT 1996 SECTION 69 APPEAL ON POINT OF LAW

Summary

The High Court, in dismissing an appeal against a final arbitration award on a point of law under section 69 of the Arbitration Act 1996, held that the obligation of Yards/Sellers to provide refund guarantee letters to Buyers under the shipbuilding contracts within 120 days – or such later date designated by Buyers – of the novation of the contracts to Buyers was an innominate term, not a condition, because the relevant provision was not expressly stated to be a condition and its wording or context did not indicate otherwise.  As a result, having opted to cancel the contracts by exercising their right to do so, and despite the admitted failure of Yards/Sellers to provide the guarantees in time, Buyers were, accordingly, not entitled to claim loss of bargain damages.

Case note contributed by Jim Leighton, LLM (Maritime Law), LLB (Hons), BSc (Hons), Solicitor Advocate of England & Wales, IMI Registered Mediator, LMAA Supporting Member and Deputy Editor of DMC’s CaseNotes

Background

Various shipping company groups entered into ten individual shipbuilding contracts (SBCs), as novated, by which each of their respective special purpose vehicle one-ship company subsidiaries agreed as Buyers to buy from various shipyard company groups as Yards/Sellers, which agreed to build and sell ten container vessels.  The SBCs had been novated to Buyers from the original buyer special purpose vehicle one-ship company subsidiaries of Yards/Sellers.

The SBCs included an agreed wording of refund guarantee letters, which were to be provided by Yards/Sellers to Buyers within 120 days of the novation of the SBCs, failing which Buyers had the option to terminate, rescind or cancel the SBCs.  The payments under the SBCs were due in three pre-delivery instalments (excluding the final delivery instalment) which were all contingent on the receipt by Buyers of the refund guarantees.  Thus, absent the refund guarantees, there was no obligation on Buyers to pay any of the pre-delivery instalments.

Yards/Sellers failed to provide the refund guarantees to Buyers within 120 days, as a result of which Buyers opted to cancel the SBCs and sought to claim loss of bargain damages, because the market prices of entering into replacement contracts in mitigation exceeded the contractual prices under the SBCs.

The disputes were referred to a tribunal of three experienced maritime arbitrators who held that Yards/Sellers’ obligation in Article X(A)(f) (fn.1) of the SBCs, to provide refund guarantees within 120 days of the novation, was an innominate term, and that - on the facts - Yards/Sellers were not in repudiatory or renunciatory breach. As a result, loss of bargain damages could not be claimed.

Buyers sought and obtained permission to appeal against the arbitration award on a sole point of law, namely whether Yard/Sellers’ obligation to provide refund guarantees within 120 days of the novation of the SBCs was a condition of the SBCs.  For the reasons explained below, the High Court dismissed the appeal.

Judgment

The Judge outlined the key facts and terms of the SBCs.  He observed that, with the SBCs having been entered into on the terms that the parties had agreed, the parties had given careful thought to the extent of the legal remedies that would be available to each other in the case of their respective contractual defaults.

The Judge noted, from the reasons of the final arbitration award, that the tribunal found Yards/Sellers to be in breach of their obligation to provide the refund guarantees within 120 days of the SBCs’ novation and that Buyers had, as a result, terminated the SBCs between 138 and 140 days after the novation.  However, the tribunal held that the obligation to provide the refund guarantees was only an innominate term, not a condition, of the SBCs and went on to find that Yards/Sellers were not in repudiatory or renunciatory breach of the SBCs.

There could be no appeal against the tribunal’s factual findings, and so the only live issue on the appeal, said the Judge, was whether the tribunal had erred in law in holding that the stipulation as to the time by which the refund guarantees were to be provided by Yards/Sellers was an innominate term, not a condition.

Having considered the leading cases on the issue of whether or not a term of a contract is a condition, the Judge concluded that United Scientific v Burnley (fn.2) and Bunge v Tradax (fn.3) were authority for the following propositions:

First, whether a stipulation as to time in a contract is to be considered to be of the essence is a question of construction of that term in the contract in which it appears, in the light of the surrounding circumstances.  Time will not be considered to be of the essence unless: (1) the parties expressly stipulate that conditions as to time must be strictly complied with; or (2) the nature of the subject matter of the contract or the surrounding circumstances clearly show that time should be considered to be of the essence.  If on its true construction a clause is a condition, it is unnecessary to consider the gravity of the breach.

Second, simply labelling the contract to be of a "commercial" or "mercantile" character is not sufficient to infer that a stipulation as to time is of the essence.  The courts should not be too ready to interpret contractual clauses as conditions unless the contract in question clearly requires the courts to do so.  However, the need for certainty in mercantile contracts is often of great importance and that fact is accordingly a factor, and sometimes may well be a determining factor, in deciding whether a stipulation as to time is a condition or not.

Third, it is necessary to balance the need for certainty in mercantile and commercial contracts on the one hand and, on the other, the desirability of not treating trivial or technical breaches as allowing rescission for breach of condition, where damages would clearly be an adequate remedy. So, if it can be seen at the time when the contract was concluded that the breaches which might occur of the relevant contractual stipulation were various, ranging from the extremely trivial to the extremely grave, then that is an indicator which points towards the term being an innominate term, and not a condition.

Fourth, in a mercantile contract when a term has to be performed by Party A as a condition precedent to the ability of Party B to perform another term, especially an essential term/condition (such as the nomination of a single loading port), the term as to time for the performance of Party A’s obligation will in general fall to be treated as a condition as Party B might thereby easily be put into serious difficulty in its ability to perform its own contractual obligation.  That is certainly an important factor in considering whether the term is a condition (referred to as "the most important single factor" in Bunge).  But, even then, whether the contractual stipulation is a condition or not still depends upon the proper construction of the contract in which the term appears, in its factual setting.

In view of those propositions and the tribunal’s reasoning in its decision, the Judge considered that the tribunal had not misstated the relevant legal principles, because the tribunal’s starting point was that a term will not be treated as a condition unless its wording or context indicate otherwise.

Further, the Judge was also satisfied that the tribunal was correct to hold that Article X(A)(f) was not a condition but rather an innominate term, because it was not stated to be a condition, which is a factor weighing in favour of the term being innominate.  The words “by no later than” – while being “the language of deadlines” – did not make Article X(A)(f) a condition without more, because it depends on the proper interpretation of the stipulation in its contractual context.

While the refund guarantees also had to be furnished within five banking days before the first pre-delivery instalment was due, which was a factor in Buyers’ favour, what militated against this alone making Article X(A)(f) a condition was that Buyers could designate in writing a date later than 120 days after the novation.  This was a factor pointing away from the clause being a condition. That was because it reflected that the parties did not treat the time limit as entitling Buyers to terminate regardless of the seriousness of the breach.

The Judge also considered there were more substantial factors militating against Article X(A)(f) being construed as a condition, when considering the nature of the subject matter of the contract and the surrounding circumstances.

The obligation for Yards/Sellers to provide the refund guarantees was not a term that had to be performed as a condition precedent to the ability of Buyers to perform an essential term of their own, because the failure to provide the refund guarantees would not derail the performance of the SBCs.  There was no obligation on Buyers to pay any pre-delivery instalments until the refund guarantees were provided, Yards/Sellers were not allowed simply to refuse to build the vessels in the event of their failure to provide the refund guarantees, and Yards/Sellers’ obligation to deliver the vessels on the contractual delivery date remained unaffected.  So, there was no interdependence between these provisions, because Buyers would not be put into serious difficulty.  This was an important conclusion the tribunal had reached; having found that the absence of the refund guarantees would not mean the SBCs would be unworkable.

The above reflected that the terms of the SBCs were carefully formulated.  Those terms also made clear that the parties did not regard the timing of the delivery of the vessels to be of the essence.  Yards/Sellers could be up to 209 days late in delivering the vessels.  In those circumstances, Buyers could only claim liquidated damages after 30 days’ delay and could not terminate until the delay extended to seven months.  As such, it made no commercial sense to hold that the parties intended Buyers to be able to treat the whole contract as at an end if Yards/Sellers provided refund guarantees 121 days, i.e. one day late, after the novation, where a long delay in building and delivery would not do so.

That the consequences of the obligation being innominate may be particularly problematic in a rising market ignored, in the Judge’s view, the comprehensive contractual remedies that had been put in place under the SBCs, dealing with delay, liquidated damages, and, ultimately, an option to terminate.  So, any feet dragging by Yards/Sellers was provided for.  If Yards/Sellers’ conduct ultimately evinced an intention not to build and deliver the vessels, then Buyers could terminate the SBCs for repudiatory breach and claim loss of bargain damages.

Conclusion

In all the circumstances, the Judge considered that the tribunal's determination that Article X(A)(f) was not a condition but rather an innominate term was correct. Thus, the Judge held that the tribunal had made no error of law and accordingly dismissed the appeal.

Comment

This judgment is a good reminder that the English courts will not easily find a term of a contract, even in the commercial and mercantile context, to be a condition, the breach of which always entitles the innocent party to terminate the contract and to claim damages for any loss of bargain resulting.

The default position is that a term of a contract is innominate, the breach of which will only entitle the innocent party to claim for loss of bargain if the breach is serious enough (by repudiation or renunciation) to terminate the contract, since the result of a breach may range from trivial to grave.

The third type of term in a contract is a warranty, the breach of which is never serious enough to be a repudiation or renunciation, as a result of which a breach will never entitle the innocent party to terminate the contract.

The Judge pointed to the following as a succinct and correct analysis of English law on determining whether or not a term is a condition (fn.4):

“i) The classification of a term as a warranty, condition or innominate term is a matter of contractual construction.

ii) The courts should not be too ready to interpret contractual clauses as conditions and unless the contract makes clear that a particular stipulation is intended to be a condition or a warranty, it should be treated as an innominate term.

iii) Where breach of a term may have a range of consequences from the trivial to the grave, that militates against that term being a condition since otherwise it would lead to results by which trivial breaches would have disproportionate consequences.”


Footnote 1:

Article X(A) set out six events under the heading "Financial Default of the Seller" by which, "in addition to any other defaults by the Seller" contained in the SBC, the Seller would be considered in default if:

“(f) The [Refund Guarantee] is not delivered to the BUYER in accordance with the terms of this CONTRACT by no later than 120 days after the date this CONTRACT is amended, novated and restated or such later date as the BUYER may designate in writing from time to time, then and in any such case the BUYER may terminate, rescind or cancel this CONTRACT by notice to the SELLER in writing or by telefax confirmed in writing in accordance with the provisions of Article X hereof.”

Footnote 2:

[1978] AC 904 (HL)

Footnote 3:

[1981] 1 WLR 711 (HL)

Footnote 4:

The Lila Lisbon [2024] EWHC 2075 (Comm), per Dias J at [23], citing The Spar Capella [2016] EWCA Civ 982 and The Arctic [2019] EWCA Civ 1161